What goes under a ground floor, and how much of it?

The whole floor sandwich in one go — hardcore, blinding, DPM, insulation, oversite and screed — off a single floor area. The layer depths are the ones the old sheet ran with; change them to suit the detail.

Measure it

Every box has its own unit next to it.

Check the rates

Rates and assumptions used

These are the figures the calculator works to. Change any of them and the order list updates — your merchant’s pack sizes and your own waste allowances beat the defaults every time.

How this one works

The figures the calculator works to. Every one can be changed in step 2, and your merchant’s pack sizes and your own waste allowances beat these defaults every time.

RateDefaultWhy
Hardcore / sand density1.7 t/m³The figure the old sheet used for both.
DPM roll coverage100 m²A 4 m × 25 m roll.
DPM laps & upstands15 %Laps at joints and the turn-up at the walls.
Insulation board2.16 m²2400 × 900. Change to 2.88 for 2400 × 1200.
Oversite ballast : cement10 :1The old sheet ran 10:1. A structural slab wants 6:1 or better — or ready-mix.
Screed sand : cement8 :1The old sheet ran 8:1 on ballast. Traditional screed is 4:1 on sharp sand.
Dry-to-wet factor1.5
Cement bag25 kg

A worked example

With the defaults the page opens on:

  • How long is the floor? 9 metres
  • How wide is it? 7 metres
  • How much hardcore? 150 millimetres
  • How much sand blinding? 25 millimetres
  • How thick is the insulation? 100 millimetres
  • How thick is the slab? 100 millimetres
  • How thick is the screed? 75 millimetres

Sub floor

  • Floor area: 63 m²
  • Hardcore: 16.06 t — 9.45 m³ × 1.7 t/m³
  • Sand blinding: 2.68 t — 1.58 m³
  • DPM: 1 rolls — +15% laps, 100 m² a roll
  • Insulation boards: 30 sheets — 100 mm, 2.16 m² a sheet
  • Total build-up depth: 450 mm — dig down at least this far below finished floor level

Oversite concrete

  • Volume: 6.3 m³ — 100 mm
  • Ballast: 14.6 t — mix 10:1
  • Cement: 59 bags — 1,460 kg
  • Or ready-mix: 7 m³ — +7.5% waste, rounded to ¼ m³

Screed

  • Volume: 4.72 m³ — 75 mm
  • Sand: 10.71 t — mix 8:1
  • Cement: 54 bags — 1,339 kg

Change any figure above and every line recalculates; the small print under each row is the sum that produced it.

Questions people ask

What are the layers under a ground floor?

Hardcore, sand blinding, a damp-proof membrane, insulation, the oversite concrete slab and the screed - the order this calculator works in. The layer depths default to the ones the old site sheet ran with; change them to the detail.

How deep is the whole build-up?

The calculator adds every layer and shows the total, so you know how far below finished floor level to dig. At the defaults that is 450 mm.

How many DPM rolls?

Floor area plus 15% for laps and the turn-up at the walls, divided by 100 m² a roll (a 4 m × 25 m roll). Both figures are in the rates panel.