How much lead flashing do I need?

Lead by code and girth, cut into pieces no longer than 1.5 m — the limit the old sheet worked to, and the one the Lead Sheet Association still gives for expansion.

Measure it

Every box has its own unit next to it.

Check the rates

Rates and assumptions used

These are the figures the calculator works to. Change any of them and the order list updates — your merchant’s pack sizes and your own waste allowances beat the defaults every time.

How this one works

The figures the calculator works to. Every one can be changed in step 2, and your merchant’s pack sizes and your own waste allowances beat these defaults every time.

RateDefaultWhy
Roll width600 mmCommon widths are 150, 240, 300, 450 and 600 mm.
Roll length3 mStandard lead roll. 6 m rolls are also sold.
Clips at450 mmHolds the free edge down in the wind.
Lap per piece100 mmMinimum 100 mm on a flashing, 150 mm on a shallow pitch.
Patination oil12 m²/LStops the white staining running down the brickwork.

A worked example

With the defaults the page opens on:

  • How long is the flashing? 8 metres
  • Which code of lead? Code 4 — general flashing
  • What girth? 300 millimetres
  • Longest piece you will use? 1.5 metres

Lead

  • Pieces: 6 no. — max 1.5 m each — expansion
  • Length with laps: 8.6 m — +100 mm lap a piece
  • Area: 2.58 m² — × 300 mm girth
  • Weight: 52.7 kg — code 4 at 20.41 kg/m²
  • Strips per roll: 2 — from a 600 mm roll
  • Rolls: 2 × 3 m

Fixing

  • Lead clips: 18 no. — at 450 mm centres
  • Lead wedges: 18 no. — into the chase at 450 mm
  • Patination oil: 1 × 1 L — about 12 m² a litre
  • Sealant: 2 tubes — pointing over the wedges

Change any figure above and every line recalculates; the small print under each row is the sum that produced it.

Questions people ask

Which code of lead do I need?

Code 4 for most flashings, code 5 for anything carrying water such as valleys and aprons, code 3 for soakers, 6 and up for exposed or parapet work. The code sets the weight per square metre the calculator uses.

Why cut lead into 1.5 m pieces?

Expansion. Longer pieces tear as they move. 1.5 m is the limit the old sheet worked to and the one the Lead Sheet Association still gives for flashings; valleys can go to 2 m.

How is the weight worked out?

Total length (run plus a 100 mm lap per piece) × girth = area, × the code weight in kg/m². Code 4 is 20.41 kg/m².