Pascoe Business SystemsPascoe Business Systems← pascoesystems.co.uk
PBS Tools

28 free tools · 25 site calculators plus HAV, 6×6 risk & accreditation · no sign-in · guidance only

All 28 tools

Groundworks · m³ · lengths

How much pipe and pea shingle for a drainage run?

A foul or surface water run: pipe lengths, the pea shingle round it, and what comes out of the trench. Bedding and surround depths follow Part H unless the drawing says different.

Measure it

Every box has its own unit next to it.

Check the rates

Rates and assumptions used

These are the figures the calculator works to. Change any of them and the order list updates — your merchant’s pack sizes and your own waste allowances beat the defaults every time.

How this one works

The figures the calculator works to. Every one can be changed in step 2, and your merchant’s pack sizes and your own waste allowances beat these defaults every time.

RateDefaultWhy
Shingle density1.6 t/m³10–20 mm pea shingle, loose.
Spoil density1.9 t/m³
Bulking30 %Swell on the spoil once it is out.
Bulk bag weight0.85 t

A worked example

With the defaults the page opens on:

  • How long is the run? 24 metres
  • How wide is the trench? 600 millimetres
  • How deep is the invert? 0.9 metres
  • Which pipe? 110 mm — foul branch
  • How much bedding under the pipe? 100 millimetres
  • How much surround over it? 150 millimetres
  • What length does the pipe come in? 6 metres

Pipework

  • Pipe lengths: 4 lengths — 24 m ÷ 6 m
  • Couplings: 4 no. — one per length
  • Bends & junctions: 0 no. — count these off the drawing — they are not in the run length

Bedding & surround

  • Surround zone depth: 360 mm — bed + pipe + surround
  • Pea shingle volume: 4.96 m³ — trench × zone × run, less the pipe
  • Pea shingle weight: 7.93 t — × 1.6 t/m³
  • Bulk bags: 10 bags — at 0.85 t

Earthworks

  • Trench dig: 12.96 m³ — width × invert × run
  • Backfill reused: 7.78 m³ — as-dug above the surround, if it is suitable
  • Surplus to cart away: 6.74 m³ — bulked 30%
  • Surplus weight: 9.85 t

Change any figure above and every line recalculates; the small print under each row is the sum that produced it.

Questions people ask

How much pea shingle do I need per metre of drain?

The trench width × (bed + pipe + surround), less the volume the pipe itself takes up, at 1.6 t/m³. For a 600 mm trench and 110 mm pipe with 100 mm bed and 150 mm surround, that is about 0.34 t per metre.

How much bedding goes under a drain?

The defaults are 100 mm of granular bed under the pipe and 150 mm of surround over the crown, which is the usual Part H arrangement. Change them if the drawing says different - the drawing wins.

How wide should a drainage trench be?

Pipe diameter plus about 300 mm is the usual minimum for someone to work in it. The calculator defaults to 600 mm.

Does it count bends and junctions?

No - it shows a row for them with a zero so you remember to count them off the drawing. They are not in the run length and no formula can guess them.

Calculators for the same job