Groundworks · m³ · t

How much concrete goes in a strip foundation?

Trench dig, concrete fill and the muck away off it, from the total run of footing. Depth and width come off the engineer’s detail — this works out what it costs to fill, not whether it is deep enough.

Measure it

Every box has its own unit next to it.

Check the rates

Rates and assumptions used

These are the figures the calculator works to. Change any of them and the order list updates — your merchant’s pack sizes and your own waste allowances beat the defaults every time.

How this one works

The figures the calculator works to. Every one can be changed in step 2, and your merchant’s pack sizes and your own waste allowances beat these defaults every time.

RateDefaultWhy
Spoil density1.9 t/m³In-situ weight of what you dig out.
Bulking30 %How much the spoil swells once it is out of the trench.
Concrete full load6 m³A full mixer. Part loads usually carry a surcharge.
Order step0.25 m³Most plants batch in quarter-metre steps.

A worked example

With the defaults the page opens on:

  • How long is the trench in total? 46 metres
  • How wide is the trench? 600 millimetres
  • How deep is the dig? 1 metres
  • How deep is the concrete? 0.6 metres
  • Spare for waste 7.5 per cent

Excavation

  • Trench dig: 27.6 m³ — 46 m × 600 mm × 1 m
  • Spoil to cart away: 14.35 m³ — (dig − concrete) + 30% bulking
  • Spoil weight: 20.98 t — × 1.9 t/m³

Concrete

  • Net concrete: 16.56 m³ — run × width × concrete depth
  • Waste allowance: 7.5 %
  • Order quantity: 18 m³ — rounded up to 0.25 m³
  • Full loads: 3 loads — at 6 m³ a load
  • Weight on the ground: 43.2 t — at 2.4 t/m³

Change any figure above and every line recalculates; the small print under each row is the sum that produced it.

Questions people ask

How much concrete does a strip foundation take?

Run × width × concrete depth, plus waste, rounded up to the batching step. For 46 m of 600 mm trench with 600 mm of concrete that is about 17.75 m³ to order at 7.5% waste.

What is the difference between strip and trench fill?

A strip footing has 225-300 mm of concrete with masonry built up off it; trench fill takes the concrete to within about 150 mm of ground level. In the calculator, set the concrete depth close to the dig depth for trench fill.

How deep should the trench be?

That is the engineer’s and Building Control’s call - 900 mm is a common minimum, deeper near trees. This calculator prices the dig and the fill for the depths on the drawing; it does not decide them.

Why does it flag when the concrete is deeper than the dig?

Because one of the two figures is wrong. It is the commonest transposition on a take-off, so the page says so rather than silently ordering the wrong amount.