Groundworks · slabs · bed · cost

How many slabs do I need for a patio?

Slabs, the mortar bed under them, jointing and a price at the bottom. Cuts are what kill a patio — 10% is sane, 15% if it is curved or laid diagonally.

Measure it

Every box has its own unit next to it.

Check the rates

Rates and assumptions used

These are the figures the calculator works to. Change any of them and the order list updates — your merchant’s pack sizes and your own waste allowances beat the defaults every time.

How this one works

The figures the calculator works to. Every one can be changed in step 2, and your merchant’s pack sizes and your own waste allowances beat these defaults every time.

RateDefaultWhy
Bed mix — sand : cement5 :1Parts of sharp sand to one of cement. 5:1 is the normal bedding mix.
Sand density1.6 t/m³
Dry-to-wet factor1.3Dry sand and cement lose about a quarter of their volume once mixed.
Cement bag25 kg
Jointing compound4.5 kg/m²Brush-in compound at a 10 mm joint. Wider or deeper joints use more.
Jointing tub20 kg

A worked example

With the defaults the page opens on:

  • How long is the patio? 6 metres
  • How wide is it? 4 metres
  • Which slab size? 600 × 600
  • Spare for cuts 10 per cent
  • How deep is the mortar bed? 40 millimetres
  • How wide are the joints? 10 millimetres
  • What does one slab cost? 9.5 pounds sterling
  • What is the laying rate? 48 £/m²

Slabs

  • Area: 24 m² — L × W
  • Coverage per slab: 0.37 m² — slab + 10 mm joint
  • Cutting waste: 10 %
  • Slabs to order: 71 no. — area ÷ coverage, +10%

Bedding & jointing

  • Bed volume: 0.96 m³ — 40 mm bed
  • Sharp sand: 1.66 t — mix 5:1, dry volume × 1.3
  • Cement: 14 bags — = 333 kg ÷ 25 kg
  • Jointing compound: 108 kg — at 4.5 kg/m²
  • Jointing tubs: 6 tubs — at 20 kg a tub

Budget

  • Slabs: 675 £
  • Laying: 1,152 £
  • Materials + labour: 1,827 £ — excludes sub base, edgings and VAT

Change any figure above and every line recalculates; the small print under each row is the sum that produced it.

Questions people ask

How many slabs do I need for a patio?

Area ÷ the coverage of one slab including its joint, plus cutting waste. A 6 m × 4 m patio in 600 × 600 slabs with 10 mm joints and 10% for cuts needs 71 slabs.

How much cutting waste should I allow?

10% on a square patio, 15% on curves, diagonals or anything with a lot of edges. Cuts are what kill a patio budget.

How deep should the mortar bed be?

30-40 mm on a full bed is normal; 50 mm if the sub base is uneven. The calculator prices the bed at a 5:1 sharp sand to cement mix, which you can change.

What is not in the budget line?

The sub base, edgings and VAT. The budget covers slabs at your price each and laying at your rate per square metre; set the laying rate to 0 for materials only.